4.1 The project will be implemented in five phases, which will take approximately 6 months to complete if all funds are available.
Phase 1 will involve installing of projectors to all classrooms, labs and department Rooms
Phase II will involve setting up of PCs in the 43 stations and networking them to the Host PC
Phase III will involve training of teachers to store notes on server and ‘moodle’ and accessing them in various classrooms
Phase IV will involve connecting the school with appropriate broadband internet connection. This will facilitate accessibility to teaching and learning resource materials through internet connectivity
Phase V will involve regular training and gathering of feedback for improvement
4.2 The following facilities and resources are already in place:
— Rooms: already have cctv cameras – new hardware can be well monitored
— Most staff have been provided a PC with internet connectivity
— There are no issues with electricity however, there needs to be good UPS for power surge, etc.